UFH design guide

Underfloor Heating Screed — The Complete Guide

Depths, mixes, first-heat schedules and the mistakes we see most often. Written for self-builders, main contractors and UFH designers.

Free quote · No obligation

Planning a UFH pour?

Name, phone, email — we'll reply the same working day with a fixed price.

Call mobile

No obligation · Same-day reply

We lay liquid and flowing screeds only. We do not offer traditional sand and cement (dry) screed.

We cover Exeter and the surrounding Devon and Somerset areas.

Or call our landline on 01392 237700

Same-day reply
Fully insured
Written quote

UFH is the single biggest reason clients switch from sand-and-cement to liquid screed. The pipework encapsulates cleanly, the cover depth drops, and the heating system responds faster once you actually turn it on.

But there's a right way and a wrong way. Every issue we get called out to remediate — cracking, curling, popped tiles, UFH runs colder than the design — traces back to a decision made at spec stage. This guide walks the whole build-up.

Recommended cover depths over UFH pipe

Build-upCover depth
Bonded to concrete slab30mm minimum over pipe
Unbonded (over DPM)35mm minimum over pipe
Floating (over insulation)40mm minimum over pipe
Suspended timber40mm cover + fibre-reinforced mix

The full UFH + liquid screed sequence

  1. 1

    Insulation

    PIR or EPS200 to Building Regs U-value. All joints taped.

  2. 2

    DPM

    1200-gauge polythene, joints taped and lapped up walls.

  3. 3

    Perimeter foam

    10mm closed-cell foam around all perimeters and up-stands.

  4. 4

    UFH pipework

    Clipped to grid at design spacing. Pressure-tested to 6 bar and left under pressure through pour and cure.

  5. 5

    Datum

    Laser levels and datum pins to true finish level, minimum cover confirmed.

  6. 6

    Pour

    Cemfloor Therm or Gyvlon Thermio+ pumped and dappled.

  7. 7

    48h no traffic

    Cover with polythene, no wind, no heaters, no forced drying.

  8. 8

    Cure & dry

    Ambient control, moisture readings taken through cure. Anhydrite: sand laitance.

  9. 9

    Commissioning heat

    First heat cycle per manufacturer schedule — usually 7–21 days depending on chemistry.

  10. 10

    Floor coverings

    Only once RH is signed off and heat cycle complete.

The five mistakes we get called to fix

  • Insufficient cover over pipes → shadow-lines and cracking above pipe runs
  • Skipping the pressure test → pinhole leaks that only show weeks later
  • Forcing drying with unvented heaters → curling and popped tiles
  • Missing the first-heat commissioning cycle → thermal shock cracking on first winter
  • Tiling before RH sign-off → adhesive failure, entire floor lifted

Get the pressure test, the cover depth and the commissioning heat cycle right and you'll never see us for a warranty visit. Skip one of the three and you probably will.

— Exeter Liquid Screeders

Liquid screed depth for underfloor heating

The minimum cover over the pipe depends on the build-up: 30mm bonded, 35mm unbonded and 40mm floating, with a fibre-reinforced mix on suspended timber. On a typical extension or new-build ground floor laid over underfloor heating we pour 50–65mm overall. Thinner than the minimum risks shadow lines and cracking over the pipe runs; deeper is fine but takes longer to dry.

Liquid screed for underfloor heating flows under and around every pipe, so there are no air pockets to slow the heat getting through. That is the main reason it outperforms hand-laid sand and cement over heating pipes.

Screed drying time with underfloor heating

Drying and commissioning are two separate things. A screed over underfloor heating can take light foot traffic after 24–48 hours, but it is not ready for coverings until it has dried and the first heat cycle has been completed. Anhydrite screeds want at least 7 days before first heat, and some designers wait 21. Cement-based screeds dry at roughly 1mm a day for the first 40mm, slowing after that.

Once the heat cycle is done we take a moisture reading and give you the figure in writing; our screed moisture testing page explains the checks.

Underfloor heating screed cost

Laying screed over underfloor heating usually adds about £2–£4 per m² to the standard rate, to cover the extra edge detailing, pipe checks and care on the day. The full indicative bands by job size are on our floor screed cost guide, and our UFH and screed package cost page explains how the two trades are usually priced together.

We pour UFH screed across Devon, Somerset and West Dorset from our Exeter base; see liquid screed in Exeter for local detail.

Frequently asked

UFH Screed Guide by county

Getting the floor ready? Read our screed floor preparation checklist before booking a pour.

Planning a UFH pour?

Send drawings and your UFH designer's spec. We'll cross-check the build-up and quote against the right screed for your programme.

Call LandlineGet a quoteWhatsApp