Screed Testing and Handover
The moment your floor is genuinely ready isn't a date on a calendar — it's a test result. Here's how we confirm it and hand it over.
Get your floor tested and signed off
Name, phone, email — we'll reply the same working day with a fixed price.
"Is it dry yet?" is the single most common question we get asked after a pour, and it's the right one to ask — but the honest answer is always a measured moisture reading, not a guess based on how many days have passed. Covering a screed too early, even by a small margin, can trap moisture and cause problems with adhesives, floor coverings or UFH performance for years afterward.
A proper handover confirms not just that the floor looks dry, but that it's measured dry to the relevant standard for whatever's going on top of it.
Here's how testing and handover work in practice.
How we confirm a floor is ready
- 1
Visual and surface check
We check for cracking, surface defects or contamination before any moisture test.
- 2
Moisture testing
A relative humidity (or equivalent) test is carried out at the appropriate depth in the screed.
- 3
Compare against the target
Results are checked against the threshold required for the intended floor covering or UFH commissioning.
- 4
Written confirmation
A result is issued in writing before you or your flooring contractor proceed.
What handover documentation should include
| Item | Why it matters |
|---|---|
| Screed product and batch reference | Traceability if any issue arises later |
| Poured depth and area | Confirms what was actually installed against spec |
| Moisture test result and date | The critical figure your flooring contractor needs |
| Any defects noted and resolution | Clear record for future reference |
Get your floor tested and signed off
We'll test, confirm and hand over your floor with proper documentation before any covering or UFH commissioning begins.
Why handover paperwork matters, not just a verbal "it's fine"
- Flooring contractors and their adhesive manufacturers often require written moisture confirmation before their own warranty applies
- It gives you a clear record if any issue is queried later in the build
- It protects the manufacturer's product warranty, which typically requires evidence of correct installation and testing
Testing & Handover — questions we get asked
More on costs and planning
Keep reading across the site
Get your floor tested and signed off
We'll test, confirm and hand over your floor with proper documentation before any covering or UFH commissioning begins.