Six-week summer window, twenty classrooms, one budget. We plan the whole programme so the school opens on time.
Schools screed in the summer holidays or not at all. That means the whole programme — strip out, insulation, UFH, screed, dry, floor covering — has to fit in six weeks.
We plan the pour sequence with the M&E contractor and floor covering team so the last classroom is ready 48 hours before term starts.
Summer programme
- 1
Week 1
Rip-out, DPM, insulation in the first block of classrooms.
- 2
Week 2
UFH manifold and pipe. Pressure test.
- 3
Weeks 2–3
Pour classrooms in batches of 4–6.
- 4
Weeks 3–5
Force-dry against the flooring programme.
- 5
Week 6
Vinyl / carpet tile down; snag and hand back.
What we bring to a school programme
- Sequenced pours so trades never wait on each other
- Daily site meetings with M&E and flooring
- Force-drying so vinyl can bond inside four weeks
- SR1 for large-format vinyl in halls
Frequently asked
Related guides
Summer works programme?
Send the room list and the flooring hand-back date. We'll build the pour schedule backwards from it.